A new connection or a change to the network has to be shown to work before the utility accepts it. We build the network model or take over an existing one, check it against measured or published data, and then run the cases the connection review asks for: normal operation, N-1 contingencies, maximum and minimum fault levels, and the harmonic picture at the point of connection.

The same studies serve owners who are not connecting anything new: industrial networks that have grown over the years, plants that have changed transformers or cables, and sites where voltage complaints or unexplained tripping point to a network problem.

What we assess

  • Bus voltages, branch loading and losses in the base case and under N-1 contingencies
  • Transformer tap settings, reactive power compensation and capacitor bank adequacy
  • Three-phase and single-phase-to-earth fault levels to IEC 60909, maximum and minimum
  • Breaking and short-time withstand ratings of switchgear, cables and transformers
  • Harmonic distortion and resonance at the point of connection, against PEA/MEA requirements
  • Voltage fluctuation, flicker and unbalance where large or fast-changing loads are connected
Scatter plot of the fault current Ik″ calculated by the network model against reference values, with every point on the line of perfect agreement
Validating the model before the connection study. The y-axis is the model's calculated fault current Ik″, plotted against the utility's published fault levels at eight points (diamonds) and against a hand calculation at 58 joints along a cable route (circles). The model agrees with the published fault levels within 0.19 % and with the hand calculation within 0.22 %.

How we work

STEP 01

Model the System

Develop or review network models, equipment data, plant models, and interconnection configurations.

STEP 02

Analyze Scenarios

Assess load flow, short circuit, voltage, loading, dynamic response, and operational conditions as required.

STEP 03

Evaluate Solutions

Compare technical options such as BESS, control changes, network reinforcement, or operating adjustments.

STEP 04

Deliver Findings

Provide engineering reports, study models, compliance documentation, and recommendations within the agreed scope.