Grid Connection, Load Flow, Short Circuit & Power Quality

Grid connection study

Large Industrial Load Connection

Load flow under normal and N-1 conditions from the 115 kV supply down to LV, capacitor bank adequacy, and a network model validated against the utility's data.

Industrial loads · 0.4–115 kV
Three charts of a modelled industrial estate, one day each in 15-minute steps: total tenant demand, total rooftop PV output and net load in MW, for a working day with typical broken cloud, a working day with severe broken cloud and a clear-sky holiday.
Demand, rooftop PV output and net load of a modelled industrial estate, built from public information. Each chart is one day in 15-minute steps: total tenant demand (solid blue), total rooftop PV output (orange) and net load, which is demand less rooftop PV (dashed red). On working days passing cloud makes the net load swing around midday; on a clear-sky holiday it falls almost to zero, the light-load case a network study has to cover alongside the peak.

Grid Code Compliance & Dynamic Simulation

Grid code compliance

Utility-Scale Solar PV Plant Compliance

Plant and plant controller models, LVRT/HVRT and frequency response simulation, reactive capability checks, and utility submission documentation.

Solar PV · 22–115 kV
Grid code compliance

Cogeneration Plant Compliance

Generator, governor, and exciter models of gas and steam turbine units based on IEEE dynamic models, with frequency response simulation against the grid code.

Gas & steam turbines · 22–115 kV
Grid code compliance

Industrial Self-Generation Solar PV

Droop and frequency response simulation for solar PV that industrial users install for their own consumption, comparing the settled output with the required droop at each test frequency.

Industrial solar PV · 22–115 kV
Four time-series charts over 200 seconds: system frequency stepping down from 50 Hz to about 48 Hz, and the active power in MW, reactive power in Mvar and rotor angle in degrees of each gas turbine unit.
Frequency response simulation of a cogeneration plant's gas turbine units. Top left: system frequency, stepped down from 50 Hz to about 47.9 Hz at 20 s and raised to 48 Hz at 80 s. Top right: active power of each unit (MW). Bottom left: reactive power (Mvar). Bottom right: rotor angle (degrees). Each colour is one gas turbine unit; every unit raises its active power after the frequency drop and settles at a new operating point.

Protection Coordination & Audit

Protection audit

Industrial Network Protection Audit & Coordination

Audit of relay settings across the network against present fault levels, coordination review, revised settings, and a prioritised relay replacement plan.

Industrial networks · 115/22 kV

Renewable & BESS Integration

Renewable integration

Rooftop PV Hosting Capacity & BESS Sizing

Quasi-dynamic simulation of distribution networks with high rooftop PV in Thailand and Southeast Asia: hosting capacity, reverse power flow, and BESS as a mitigation option.

Rooftop PV & BESS · 0.4–22 kV
Diagram of a modelled industrial estate: a 115 kV supply to a 115/22 kV intake substation, a cogeneration plant and BESS on the 22 kV switchboard, and five 22 kV feeders along the estate roads to the tenant plots. Each plot is drawn to its contracted load, with a blue square for its rooftop PV capacity on the same scale.
Feeder layout of a modelled industrial estate, built from public information. Each tenant plot is drawn to its contracted load and its blue square to its rooftop PV capacity, on the same scale. Where the squares nearly fill the plots, rooftop PV exceeds the load on that feeder and power flows back towards the substation at midday, so the feeders that limit hosting capacity stand out before any simulation is run.

Feasibility & Planning

Hybrid plant study

Solar PV + BESS Feasibility & Operating Strategy

Evaluation of net energy sales, shortfall, curtailment, and battery sizing under PPA terms, with NPV and sensitivity analysis.

Solar PV & BESS · 22–115 kV
Energy storage roadmap

Grid-Scale Energy Storage Roadmap

Cost-benefit assessment across substations, power system studies, and development of an energy storage roadmap.

Substation BESS · 22–115 kV
Microgrid planning

Microgrid Investment Planning & EMS Design

Least-cost generation and storage mix, reliability assessment with LOLE and ENS, and design of the energy management system that runs the microgrid.

Solar PV, BESS & diesel · 0.4–22 kV
Imbalance assessment

Direct PPA Imbalance Cost & BESS Simulation

Slot-by-slot settlement of produced energy against the declared schedule within the trade window, the imbalance cost of forecast error under a Direct PPA's penalty bands, and BESS simulation to cut penalties and recover curtailed energy.

Solar PV · 22–115 kV
Imbalance analysis dashboard: summary cards for net revenue and imbalance impact in THB, energy produced in MWh and forecast error as NMAE; a line of slot counts; a histogram of 15-minute slots by signed error, coloured by penalty band; inflow and outflow energy bars; and tables of shortfall cost by penalty band and of curtailed energy.
An example imbalance analysis in Enserve over ten days of 15-minute slots, settled only inside the daily trade window: in each slot, the energy declared to the customer is compared with the energy produced. Left: the number of slots in each error range (negative where production fell short of the declared energy), coloured by penalty band, and below them the shortfall cost in each band. Right: the energy flow, balancing production and the shortfall bought from the grid against the energy delivered to the customer, the curtailed surplus and off-contract production. The top row gives net revenue, the cost of imbalance and the forecast error as NMAE (% of capacity).

Owner's Engineer & Project Advisory

Owner's advisory

Power Management System Owner's Engineer

Technical design review, procurement advice, test-document review, FAT/SAT support, and handover advisory.

Power management systems · 22–115 kV

Custom Digital Platforms

Renewable forecasting

Wind & Solar Forecasting and Data Submission

Machine-learning forecasts of wind and solar plant output, checked against measured generation, with automated data submission in the format the grid code requires.

Wind & solar plants · 22–115 kV
Line chart of a solar plant's AC output over about eight days in hourly steps: the actual output in blue and the forecast in orange, both falling to zero every night and following each other closely on most days.
Forecast against actual output of a solar plant in Enserve's error analysis, hour by hour over about eight days. The actual AC output is in blue and the forecast in orange. Both series run on through the night at zero, without gaps, and the forecast follows the shape of each day, including the days when output peaks far lower than the rest.
Validation screen of a solar forecasting model: a row of metrics (R², RMSE, MAE, MAPE and MBE, with the training and test sample counts), a scatter chart of predicted against actual output lying close to the diagonal, and a histogram of forecast errors concentrated around zero.
Validation of a solar forecasting model in Enserve on a held-out test period that the model did not see in training. The top row gives R², RMSE, MAE, MAPE and MBE and the number of training and test samples. Left: predicted against actual output; points on the dashed diagonal are exact forecasts. Right: the distribution of the forecast errors, most of them in the bins around zero.

Let's solve your energy challenge.

Discuss a power system study, renewable integration assessment, forecasting workflow, or grid simulation requirement with GGSC.

Contact GGSC ↗